Cargo unloading from container vessels begins at Thilafushi

MPL also cited tourism growth, increased bed capacity, and new resorts as drivers of higher imports.

Featured Image

Two MPL employees walking through that area as container unloading work takes place today at Thilafushi cargo port.---Photo: Nishan Ali| Mihaaru

Shazma Thaufeeq

2026-11-25 23:26:35

Maldives Ports Limited (MPL) has stated that cargo unloading from container vessels has officially begun at the Thilafushi Cargo Terminal.

MPL stated that for the first time, a large container-carrying vessel docked and unloaded cargo at the Thilafushi Cargo Terminal, where operations of the Malé Commercial Harbour are being fully relocated.

MPL stated that for the very first time in the history of the country's commercial port, the container vessel "MSS Galina" docked at Thilafushi first. That vessel arrived in the Maldives with 524 containers of cargo. Out of the containers brought by that vessel, 490 TEUs are scheduled to be unloaded directly at the Thilafushi Cargo Terminal, according to MPL.

MPL began the necessary preparations and planning work to conduct such an operation in Thilafushi in May of this year. MPL stated that this decision was made at the time because, generally around the New Year and up to one month after the end of Ramadan, the volume of goods imported into the Maldives increases significantly.

MPL also stated that the expansion of the Maldives' tourism sector, increase in bed capacity, and opening of new resorts are also key reasons why the volume of imported goods increases.

Work unloading containers at Thilafushi's cargo port taking place today.---Photo: Nishan Ali| Mihaaru

MPL stated that one of the biggest purposes of expanding the operations of the Thilafushi Cargo Terminal is to provide an adequate, swift relief to the space constraints faced by the Malé commercial port. The company also stated that facilitating arrangements so that businesses can clear goods as quickly as possible without any difficulties is another reason for starting cargo unloading at Thilafushi.

Senior officials of the company giving information to the media regarding unloading cargo at Thilafushi commercial port.---Photo: Nishan Ali| Mihaaru

Practical work on the massive project to completely relocate Malé's commercial port to Thilafushi is already progressing rapidly. Specifically, work on building the initial 375-meter quay wall being developed first at the Thilafushi port is being carried out by the renowned Chinese company "China Harbour Engineering Company." It is projected that this work can be completely finished by the end of July next year.

MPL stated that the goal is to relocate all operations of the Malé commercial port to Thilafushi during November next year and begin providing services at a modern standard.

MPL also stated that the operation launched today is a very strong and successful foundation laid toward achieving that important goal.

A vessel docked at Thilafushi Cargo Port.---Photo: Nishan Ali| Mihaaru

Some additional information related to relocating the port to Thilafushi

  • In the work to relocate the Malé commercial port to Thilafushi, work on the first 100 meters of the quay wall dedicated to domestic vessels has now been completed. And approximately 40 percent of backfilling the reclaimed area of the domestic quay wall has been completed.
  • Work is currently underway on producing the precast concrete blocks required for the quay wall on-site and procuring needed machinery and equipment, in addition to selecting a contractor to construct the terminal buildings.
  • When the 60-hectare port established in Thilafushi opens, it will create space to handle containers at a capacity of 390,000 TEUs per year. This figure will increase container capacity to 1.8 million TEUs per year.
  • The port will open with a 375-meter-long quay wall dedicated to international container vessels with a depth of 14.6 meters. There will be room to extend this quay wall to 1.4 kilometers.
  • At Thilafushi port, a quay wall of roughly more than two kilometers dedicated to domestic vessels will be built.
  • Along with building the 375-meter-long quay wall dedicated to international container vessels established at this port, loading and unloading cargo can be shortened to a "turnaround time" of approximately two days.
  • It has also been decided to install two ship-to-shore quay cranes and one mobile harbor crane when Thilafushi port opens.

President Dr. Mohamed Muizzu has stated that Thilafushi Port will expand fourfold compared to the Malé commercial port, and that it is the largest economic project currently underway in the Maldives.